Improvements

2019.09.08 - The BETONIQ Quality System is being migrated from Google Docs to traditional HTML.
2019.09.08 - Date in Quality Blog reversed: yyyy.mm.dd
2015.07.23 - Layout improved (made suitable for mobile phones), "BetoniQ" replaced by "BETONIQ".
2013.11.15 - All meetings added to §3 Terms and Definitions.
2013.11.14 - Remarks Andy 29-10-2013 regarding Pr2 Production copied.
2013.11.14 - Board of Directors changed everywhere in Executive Board.
2013.11.14 - Wi07 Registration Project + Acquisition Information adjusted to Pr1 Acquisition, Development and Sales.
2013.11.10 - Assistants removed from Project Preparation Meetings and Pr2 Production. I don't see why the Factory Manager should attend and it is not clear to me how the production planning is being set up and discussed, so I didn't change the rest of the Project Preparation Meetings yet.
2013.11.10 - USM (Upstart Meeting) included in Pr2 Production and BETONIQ JV - Project Preparation Meeting. USM also mentioned in §3 Terms and Definitions. (Remark Andy 29-10-2013).
2013.11.10 - Job description Site Stores Foreman, Site Stores Assistant, Production Stores Supervisor and Production Stores Assistant adjusted, also in §3 Terms and Definitions. (responsible for measurements, Remark Andy 16-10-2013).
2013.11.10 - Job description Linesman adjusted, also in §3 Terms and Definitions. (responsible for measurements, Remark Andy 16-10-2013). The exact order procedure will be described in Wi08 Budget Management and Contracts.
2013.11.10 - Job description Project Surveyor adjusted, also in §3 Terms and Definitions. (responsible for measurements, Remark Andy 16-10-2013).
2013.11.07 - Wi04 Relation Management is finished.
2013.10.27 - Fo11 Delivery Statement and Checklist added.
2013.10.27 - Project Preparation Meeting added.
2013.10.27 - BETONIQ Security Program added.
2013.10.27 - Pr2 Production is finished.
2013.10.20 - Internal Meetings and Evaluations+Wi02 Internal Evaluations finished. Menu-item "Meetings" added.
2013.10.19 - Forms Fo01 - Fo06 created and linked.
2013.10.19 - Meetings Menu-item created with sub-menu pages.
2013.10.19 - Pr1 Acquisition, Development and Sales is finished.
2013.10.15 - Quality System Handbook is finished.
2013.10.15 - Layout Acquisition and Project Sheets improved.
2013.10.14 - All Job Descriptions are finished.
2013.10.14 - Job Descriptions of the Facility Management unit are finished.
2013.10.14 - Job Descriptions of the Site Stores unit are finished.
2013.10.14 - Job Descriptions of the Foundation Work unit are finished.
2013.10.14 - Job Descriptions of the Infrastructure unit are finished.
2013.10.14 - Job Descriptions of the Carpentry unit are finished.
2013.10.14 - Job Descriptions of the Painting unit are finished.
2013.10.14 - Job Descriptions of the Tiling unit are finished.
2013.10.14 - Job Descriptions of the MEP unit are finished.
2013.10.13 - Job Descriptions of the Erection unit are finished.
2013.10.09 - Job Descriptions of the Production Maintenance unit are finished.
2013.10.09 - Job Descriptions of the External Transport unit are finished.
2013.10.08 - Job Descriptions of the Production Security unit are finished.
2013.10.08 - Job Descriptions of the Weighbridge unit are finished.
2013.10.08 - Job Descriptions of the Laboratory unit are finished.
2013.10.08 - Job Descriptions of the Production Stores unit are finished.
2013.10.07 - Job Descriptions of the Mixing Plant unit are finished.
2013.10.07 - Job Descriptions of the Loading unit are finished.
2013.10.07 - Job Descriptions of the Stockyard unit are finished.
2013.10.06 - Job Descriptions of the Additional Production Services unit are finished.
2013.10.06 - Job Descriptions of the Concreting unit are finished.
2013.10.06 - Job Descriptions of the Moulds unit are finished.
2013.10.06 - Job Descriptions of the Reinforcement unit are finished.
2013.10.05 - Job Descriptions of the Project Supervision unit are finished.
2013.10.05 - Job Descriptions of the Project Surveying unit are finished.05-10-2013
2013.10.05 - Job Descriptions of the Project Safety Control unit are finished.
2013.10.04 - Job Descriptions of the Project Quality Control unit are finished.
2013.10.04 - Job Descriptions of the Production Supervision unit are finished.
2013.10.04 - Job Descriptions of the Production Planning unit are finished.
2013.10.04 - Job Descriptions of the Production Surveying unit are finished.
2013.10.01 - Job Descriptions of the Production Training unit are finished.
2013.10.01 - Job Descriptions of the Production Safety Control unit are finished.
2013.10.01 - Job Descriptions of the Production Quality Control unit are finished.
2013.10.01 - Job Descriptions of the Design department finished.
2013.10.01 - Job Descriptions of the Sales department finished.
2013.09.21 - Job Description General Manager, Factory Manager and Senior Project Manager are revised.
2013.09.21 - Job Descriptions of the HR & Administration department finished.
2013.09.20 - Job Descriptions of the Finance & Legal Affairs department finished.
2013.09.20 - Job Description CEO revised.
2013.09.20 - First Job description (Production Supervisor) finished.
2013.09.19 - Salary Scale finished.
2013.09.19 - All Job Description Pages created and linked to, (but are without the proper text yet).
2013.09.11 - All Department and Unit pages finished.
2013.09.08 - Description Design department plus job descriptions finished.
2013.09.08 - Default Format Minutes Created.
2013.09.07 - Several Ov01 Function Descriptions (like Design Manager) added.
2013.09.04 - Ov01 Persons an Assignments Overview BETONIQ Ghana Ltd. implemented.
2013.09.01 - New Organization Chart finished.
2013.08.18 - Risk Management added to the intranet.
2013.08.12 - Acquisition and Project sheets added, new project coding with "BG-" in front.
2013.08.08 - Ghana Building Code added to the intranet.
2013.07.23 - Acquisition Lists and Projects Lists updated.
2013.07.19 - Joint Venture - Department - Factory structure implemented.
2013.07.18 - Total update
2013.06.27 - Task List Implemented.
2012.12.20 - Total update
2012.12.18 - New company name, changed board and new logo processed.
2012.04.04 - New company name, changed board and new logo processed.
2012.02.07 - New layout with logo for the intranet.
2012.01.22 - Wi02 Internal Meetings and Assessments added.
2012.01.21 - Board of Directors added.
2012.01.21 - Agenda BETONIQ Board Meeting added.
2012.01.21 - Agenda BETONIQ Shareholders Meeting added.
2012.01.17 - All job references in Pr1 Acquisition, Development and Sales are added.
2012.01.16 - Ov01 BETONIQ Hub - Acquisition Manager Added.
2012.01.16 - Pr4 Problem Registration Added.
2012.01.16 - Wi01 Problem Registration Added. 2012.01.15 - Quality System Blog Added.
2012.01.15 - Quality System is operational.



goto top